Il Saint-Jean-de-Maurienne site
Home | Construction sites | Saint-Jean-de-Maurienne site
MULTIMODAL HUB | WORK IN PROGRESS
Since January 2019, work has been underway on the transitional multimodal hub that will substitute the current station until the connection to the existing railway line by the new base tunnel on the Lyon-Turin line.
In order to support travelers and keep the bus and train stations working during the works, TELT and SNCF Réseau will create a transitory multimodel interchange hub which will be operational until 2021, and will facilitate connections with the other transport systems.
Multimodal pole
The construction will comprise a bus station, a building for passengers with counters and a waiting room, car and bike parking spaces, urban bus stops, a dedicated taxi rank and new points of access to the railway station platforms.
Subsequently, the provisional station will become the new definitive international station by 2030.
Data key

2019-2022: duration of the construction site

2022-2027: temporary setting

2030: inauguration of the international station

200.000 cubic meters of filling materials
News from the sites

10.5 km of France-side base tunnel completed
With the 10.5 km base tunnel completed on time and on budget TELT presents Mission-S, the programme to improve safety at work.

Axel arrives in Chiomonte
The CIM 4.0 competence centre has created for Webuild the first autonomously-guided robot to safely explore the deepest area of the gallery.

The multimodal interchange hub in Saint-Jean-de Maurienne will become operational in mid-June
Above ground and underground works are in progress in France and Italy.

A new major construction site for the Lyon-Turin base tunnel
Mission-S: TELT and companies sign pact for accident prevention and workers’ health