La Praz site
Home | Construction sites | La Praz site
ACCESS ADIT | 2,7 KM | WORK COMPLETED
With a length of 2,800 m and a 12% down gradient, the access adit of La Praz is located on the right bank of the River Arc and is divided into two sections, the second being parallel with the future base tunnel.
Progress

The La Praz access adit is located in the municipality of Saint’André, and was tunneled using a traditional technique (explosives) between 2005 and 2009 involving about 110 direct workers, 49% of whom were from the Rhône-Alpes region. Once the base tunnel becomes operational, the access adit will serve as a ventilation duct, and as a maintenance and safety passage.

Management of water seepage
In geological terms, the data collected reveals excellent rock reliability. The hydrological conditions included underground aquifers in the first 500 metres of excavation which had to be managed by testing the most appropriate solution in order to limit interference with surface water resources. As a result, resin was injected inside the tunnel in order to reduce water seepage and guarantee reduced permeability in the tunnel.
Data key

2.700 m of length

2005-2009: duration of the worksite

12% slope

110 direct workers
News from the sites

10.5 km of France-side base tunnel completed
With the 10.5 km base tunnel completed on time and on budget TELT presents Mission-S, the programme to improve safety at work.

Axel arrives in Chiomonte
The CIM 4.0 competence centre has created for Webuild the first autonomously-guided robot to safely explore the deepest area of the gallery.

The multimodal interchange hub in Saint-Jean-de Maurienne will become operational in mid-June
Above ground and underground works are in progress in France and Italy.

A new major construction site for the Lyon-Turin base tunnel
Mission-S: TELT and companies sign pact for accident prevention and workers’ health