Chronology of works
Home | Chronology of works
2022

10.5 Km of France-side base tunnel completed
April
TELT assigns the project management of the international stations in Italy and France
April2021

Contracts assigned for France-side base tunnel
July
Work continues on 7 construction sites between Italy and France
May
Construction site of the new car and truck terminal in San Didero begins
April
Tender for the project management of the Chiomonte junction and the car and truck terminal
March
Third phase of land acquisition in Chiomonte
February2020

Chiomonte construction site, phase 2 of enlargement completed
November
A new René-Cassin railway bridge
November
10 km of the base tunnel already dug
October
Consolidation of the embankments along the Arc River
August
Contracting of the base tunnel ventilation shafts
July
Launch of work to widen the Chiomonte site
June
Remodelling the Lyon-Turin activities in light of the Coronavirus emergency
April
Work has started in Salbertrand
April